
Progress Update from LakeVu Condos in Barrie
Shoring is now 100% complete and phase 1 construction continues to progress at 11 Lakeside Terrace in Barrie.

Formwork and Rebar contractors started work on Aug 26, 2019, beginning from the N/W corner perimeter footing moving in a clockwise direction.

Waterproofing contractor is scheduled to start work on Sept 11, 2019.
The tower crane has been scheduled to be operational by Oct 3, 2019.